A missed delivery date leaves a property buyer with decisions that cannot always wait for construction to finish. Should another instalment be paid, a revised timetable accepted, or a formal claim started? A lawyer in Dubai can assess those choices by identifying the obligation that has fallen due and the remedy the evidence supports. Delay alone does not establish an automatic refund or a fixed compensation entitlement.
Begin with the signed sale and purchase agreement and every subsequent amendment. Make a separate entry for the estimated completion date, the contractual delivery date and any permitted extension. Record the conditions attached to each extension, including notice requirements. A grace period written into one agreement should not be assumed to apply to every project.
Check what delivery requires under the agreement. A construction milestone, an invitation to inspect and an offer to transfer possession may describe different events. Preserve the original documents alongside later correspondence so that a revised date can be traced to an agreed amendment or a particular contractual provision.
Article 7 of Executive Council Resolution No 6 of 2010 addresses completed projects with the necessary completion certificate. A developer may not withhold handover and registration from a purchaser who has fulfilled the relevant contractual obligations. Evidence of certification and buyer compliance therefore matters when construction is complete but possession remains disputed.
Request a written account of the outstanding work, the reason for delay and the contractual basis for any extension. Ask how the event affected this project and the proposed delivery programme. General statements about difficult conditions give little assistance in assessing whether the particular extension is justified.
The current Civil Transactions Law is Federal Decree Law No 25 of 2025, effective from 1 June 2026. Its temporal rules require separate consideration of earlier facts and acts. Where applicable, Article 236 addresses force majeure that makes performance impossible. A notice using that expression does not, by itself, establish that the legal conditions are satisfied.
Dubai Land Department reported 124 completed real estate projects with a total value of AED 27.5 billion in 2025, alongside 937 projects under construction. These emirate-wide project counts do not measure whether an individual handover was on time. Check the recorded status of the particular project against its contractual delivery requirements.
Use the Dubai Land Department Project Status Enquiry to obtain the recorded project details and completion percentage. Save a dated result using the correct project name or number. Compare it with the developer correspondence and ask about material differences. Overall progress does not answer every question about the readiness of your individual unit.
An active project running behind schedule requires a different assessment from a project subject to regulatory cancellation. DLD explains that it cannot terminate an individual sale contract at the request of a buyer in a project that has not been cancelled; judicial relief requires the appropriate proceedings. Ask for documentary confirmation of any reported cancellation or referral.
Decide whether you still want the unit, need a workable delivery commitment, or wish to pursue termination. Under Article 234 of the current Civil Transactions Law, a party facing a due but unperformed reciprocal obligation may, after notice, seek performance or rescission through the court. The court has discretion, and compensation requires justification. Missing the date does not compel the court to terminate.
A lawyer in Dubai can prepare a demand that identifies the obligation, supporting documents and requested response. Articles 337 and 338 also make formal default and its exceptions relevant to compensation. An informal complaint should not be assumed to satisfy every applicable notice requirement.
Record each additional expense separately, with its date, amount, supporting invoice and explanation of its connection to delayed delivery. Distinguish costs incurred because of the delay from costs you would have paid anyway. For an income claim, retain evidence supporting the proposed letting period and amount rather than relying only on advertised rental returns.
Article 339 provides for assessment by reference to damage actually sustained where compensation is not determined by law or contract. If the agreement contains a predetermined compensation clause, Article 340 permits judicial adjustment in specified circumstances. Neither the claimed total nor the contractual figure should be presented as an assured recovery.
Review payment obligations before withholding instalments. Article 222 concerns reciprocal obligations that are due for performance; it is not a general permission to stop every payment whenever construction slows. Keep receipts, requests for payment and any default notices together. Review proposed amendments for their effect on existing claims before signing.
The correct forum requires review of any valid arbitration agreement and the nature of the dispute. Separately, Decree No 33 of 2020 provides a special tribunal framework for qualifying unfinished and cancelled projects outside the DIFC. A lawyer in Dubai should check that framework before commencing ordinary proceedings or assuming an arbitration clause resolves every jurisdiction question.
No. It helps establish project progress. The contractual delivery requirements, completion certification and buyer obligations must also be examined.
Read the complete amendment first. Check whether it changes only the timetable or also settles compensation, releases existing claims or introduces further conditions. Keep a signed copy.
Do not assume a fixed payment date. Confirm the official decision and applicable liquidation or tribunal process. The available funds, verified payments and relevant orders affect how recovery proceeds.
Record the project and unit identifiers, the original delivery terms, every agreed amendment, payment dates, progress updates and notices. Keep the underlying documents beside the chronology. Distinguish a reported construction milestone from an agreed delivery date or an actual offer of possession.
Identify the amount or other remedy offered, the payment or delivery timetable, and which existing claims the agreement would settle. Check any release, waiver or new condition before signing. Keep a complete signed copy and obtain advice on how the proposal affects the rights already in dispute.